On the Designing and Applying Process of Establishing Program
摘要
在设计人员的密切配合下
经过9个月的辛勤劳动
机关附属用房翻建项目的规划申报审批工作得以完成
终于领到了《建设工程规划许可证》。其间涉及很多部门
而各个部门对设计报建的要求各不相同
这些要求作者认为对设计人员具有很大的参考价值
如果我们的设计人员在设计阶段多考虑这方面的情况
对业主的设计报建工作则有极大的帮助。
Abstract
With the friendly cooperation of engineers as well as 9-month laborious efforts
the program of re-establishing the apartments appertaining to our ministry has been finally approved. And we have got The Permit of Building Program at last. During this period
many departments have been involved in the process of applying. Their different requirements on the designing and applying issues
in my opinion
are very valuable to be the reference of designers. If our engineers can take more consideration of those aspects in the stage of designing
it will be greatly helpful for the designing and applying work of buildings’ owners. Now I would like
therefore
to publish the written record of this process with the aim of making exchange with my colleagues. And I am open to all your ideas.